WWTP Dayri industry 500 m3/day in Palencia (Spain).
The turnkey project is designed for the treatment of 500 m3 / day, although it has been dimensioned with a view to a future expansion of water treatment flow to 600 m3 / day.
The building which home the equipments has been built at two heights in laminated prefabricated panels, mainataining the aesthetics and archetexture to the factory.
The Wastewater treatment plant consists of a pretreatment with rotary screen, which will eliminate part of the solids 0.50 mm, W-Tank® homogenization tank from which the water is pumped to a physical-chemical treatment by dissolved air flotation technology. The process ends with a SBR biological treatment in W-Tank® to reduce the load to the permissible levels of dumping.
The management opted for this type of tanks for its simplicity and speed in assembly. Biological treatment was necessary to reduce the load to the permissible levels of discharge to the public channel.
The dissolved air flotation unit has capacity of 30 m3/ h. The sludge generated in this process of wastewater treatment will be dehydration by an Automatic Press Filter, with which the dryness increase, make easy its management.
After the start up of the treatment plant, Aguambiente’s maintenance team offers training sessions to the customer on “best practices for the operation of the WWTP”. The training is aimed at the personnel who will operate the plant in order to maximize performance and help reduce operating costs.
You can see more references here.